Cross Passage Headwall Construction near Duncannon Drive - Stage 1

What we are building

What: A cross passage is a tunnel cut between two other parallel tunnels required for maintenance or emergency purposes. Crews will be building one headwall for the future cross-passage required for future maintenance of the tunnels.  Read more »

September 032014

Open houses in September

Metrolinx is hosting three open houses in September at various locations along the Eglinton corridor to provide an update on current Crosstown construction.

Join us at one of the following sessions to hear what is happening, why it needs to happen and how it may impact you:

Tuesday, September 9, 2014

7:00 - 9:00 pm Read more »

August 052014

Short Term Lane Closures along Eglinton Avenue West for Monitoring Equipment Installation Black Creek Drive -Yonge Street Summer 2014 - Summer 2015

What work is starting?

What: Crews will be installing ground movement monitoring equipment.
 
Why: Monitoring equipment will provide information on the ground conditions during excavation and tunnelling activities to the construction team. Read more »

July 242014

Cross Passage Headwall Construction near Duncannon Drive - Stage 1

What we are building

What: A cross passage is a tunnel cut between two other parallel tunnels required for maintenance or emergency purposes. Crews will be building one headwall for the future cross-passage required for future maintenance of the tunnels.  Read more »

July 182014

Update: Cross Passage Headwall Construction near Vesta Drive - Stage 1

What we are building

What: A cross passage is a tunnel cut between two other parallel tunnels for maintenance or emergency purposes. Crews will be building one headwall for the future cross-passage required for future maintenance of the tunnels. Read more »

Or, let us help you Experience Eglinton. Choose a category to explore the neighbourhood:

Syndicate content