Thank you for attending the Central West Open House on October 28, 2019. For those who weren't able to make it out in person, the presentation is here:
On Wednesday October 30, 2019 beginning at 4:00 a.m. crews will close the Hilltop Road-Bathurst Street laneway behind the Forest Hill Station Secondary Entrance to conduct a concrete pour. The concrete will form the exterior wall of the Secondary Entrance. The pour is one of a series of concrete pours that will take place in 2019 to construct the Secondary Entrance. Read more »
*THIS WORK WAS POSTEPONED UNTIL OCTOBER 30* Read more »
THIS WORK HAS BEEN POSTPONED Read more »
What Work is Taking Place? Read more »
Overnight lane reductions will be on Eglinton Avenue at Bathurst Street the week of October 7, while crews perform watermain work. No overnight work is planned for the evening of Tuesday October 8thRead more »
The construction liaison committee meeting of Cedarvale & Forest Hill was held on September 25, 2019. You can see the presentation here:
What Work is Taking Place? Read more »
What Work is Taking Place?
Crews will conduct two separate concrete pours, one in August and one in September 2019, without the need for an intersection closure. The concrete will form part of the future roof of Forest Hill Station.
To ensure the continuity of the pour, and to minimize the impact to the travelling public, each pour will begin overnight when traffic is lighter. Construction notices will be issued in advance of each concrete pour. Read more »
What Work is Taking Place?
The intersection of Bathurst Street and Eglinton Avenue West will be closed while crews complete a large concrete pour at Forest Hill Station. The concrete will form part of the future roof of the station. The closure will take place on Friday, August 23, 2019 and continue into the following day. The concrete pour will take approximately 18 hours to complete. Once the work is complete, the intersection will re-open. Read more »