Crosstown

Birchmount Road

May 292019

Updated: Construction Begins for Traction Power Substation 12

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be commencing construction of the Traction Power Substation (TPSS) 12 that will power the Eglinton Crosstown Light Rail Transit (ECLRT) line. The work will take place in a fenced work zone located on the north east side of Birchmount Road in close proximity to Toronto Police Service 41 Station. Read more »

May 282019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on May 28, 2019. You can see the presentation here:

Read more »

April 302019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant stations was held on April 30, 2019. You can see the presentation here:

Read more »

April 112019

Eastern Works Open House

Thank you for attending the Eastern Work Open House on April 10, 2019. For those of you who missed it, the presentation is here:

Download the presentation

April 102019

OVERNIGHT UTILITIES RELOCATIONS AT BIRCHMOUNT ROAD AND EGLINTON AVENUE EAST

WHAT WORK IS TAKING PLACE?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road. Read more »

April 042019

Upcoming South Sidewalk Closure - Sinnott Rd to Birchmount Rd - April 15, 2019

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting civil road work in relation to road widening works on the south side of Eglinton Avenue East between Sinnott Road and Birchmount Road.  Starting as early as April 15, 2019 and lasting for approximately one (1) month.

There will be a sidewalk closure on the south side of Eglinton Avenue East between Sinnott Road and Birchmount Road in order to safely carry out the work. Read more »

Categories:
March 292019

Construction Notice: Overnight Utilities Relocations at Birchmount Road

OVERNIGHT UTILITIES RELOCATIONS AT BIRCHMOUNT ROAD AND EGLINTON AVENUE EAST

 

WHAT WORK IS TAKING PLACE?

 

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road.

  Read more »

March 262019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on March 26, 2019. You can see the presentation here:

Read more »

March 212019

Sidewalk Closure for Massey Creek Culvert Work

Sidewalk Closure for Massey Creek Culvert Work

 

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews will be replacing the existing culvert at Massey Creek. Work began as early as late February 2019 and will last for approximately nine (9) months. The creek is located at the signalized intersection of Eglinton Avenue East and Rosemount Drive. Read more »

March 132019

Updated: Guideway Work along Surface Section of the Eglinton Crosstown LRT: Warden Avenue to Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the center of Eglinton Avenue East between Warden Avenue and Birchmount Road. Starting as early as March 16, 2019 for approximately eight (8) months.

The work includes cutting and removal of existing asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops.  Read more »

Or, let us help you Experience Eglinton. Choose a category to explore the neighbourhood:

Syndicate content