Original Issue Date: October 24, 2017
Repost & Update Date: November 27 and December 8, 2017
Repost & Update (2) Date: January 5, 2018
What Work is Taking Place? Read more »
Sanitary sewer relocation work on Eglinton Avenue East between Brentcliffe Road and Leslie Street has been cancelled due to weather.
Updated: December 8, 2017
Previous Update Issued: November 27, 2017
Original Issue Date: October 24, 2017 Read more »
What Work is Taking Place?
Crews will be pouring the concrete foundation and roof slabs for the Brentcliffe Portal. Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 4:00 a.m. in order to reduce impact to traffic in the area. Read more »
Thank you for attending the open house about Science Centre Station and West At-Grade (Sunnybrook Park Stop to O'Connor Stop) on November 14, 2017. Read more »
What Work is Taking Place?
Crews will relocate an existing sanitary sewer line on Eglinton Avenue East between Brentcliffe Road and Leslie Street to support the upgrade of existing infrastructure at the future Brentcliffe Portal and Sunnybrook Park Stop. Read more »
What Work is Taking Place?
As part of the ongoing construction works for the future Brentcliffe Portal and Surface Stops, above ground and in-ground monitoring points will be installed on the City Right-of-Way, which may include the roadway, sidewalks and/or driveways on Thursfield Crescent.
Once installed, the instruments will remain at these locations for the length of the project. Monitoring allows crews to evaluate the impact of construction works. Read more »
What Work is Taking Place?
Crews will relocate an existing sanitary sewer line on Eglinton Avenue East between Brentcliffe Road and Leslie Street to support the upgrade of existing infrastructure at the future Brentcliffe Portal and Sunnybrook Park Stop. Read more »
The construction liaison committee meeting of Brentcliffe - Victoria Park was held on November 2, 2017. You can see the presentation here:
What Work is Taking Place?
Crews will relocate and upgrade existing overhead and underground telecommunication and hydro utilities between Brentcliffe Road and Leslie Street along Eglinton Ave East in preparation for construction of the Brentcliffe Portal and Sunnybrook Park Stop. Read more »
What Work is Taking Place?
Crews will relocate an existing sanitary sewer line on Eglinton Avenue East between Brentcliffe Road and Leslie Street to support the upgrade of existing infrastructure at the future Brentcliffe Portal and Sunnybrook Park Stop.
To minimize traffic disruption for the community, transit users and local businesses, this work is being done overnight. Paid Duty Police Officers will maintain safe traffic flow. Read more »
Experience Eglinton by street: