Crosstown

Brentcliffe Road

May 102017

Ongoing Preparatory Works between Brentcliffe Road and Midland Avenue: Street Furniture Removals SPRING & SUMMER 2017

What Work is Taking Place?

As part of ongoing preparatory works, crews will begin the process of removing street furniture across the Eglinton Avenue East corridor between Brentcliffe Road and Midland Avenue. Read more »

April 202017

Decommissioning and Bell Utility Works at Brentcliffe Road Launch Shaft Site

Over the last few months, the tunnel contractor has begun decommissioning the Launch Shaft site at Brentcliffe Road to make way for the station contractor. There will be no change to the footprint of the site. However, as tunnel work has concluded, preparatory works will now begin for the next phase of LRT construction. Read more »

January 182017

Ongoing Occasional Evening Works: Eglinton Lane Reductions between Brentcliffe Road and Leslie Street

What Work is Taking Place?

Beginning as early as late January 2017, crews will conduct geotechnical monitoring on Eglinton Avenue East between Brentcliffe Road and Leslie Street to support construction of the Laird and Science Centre Stations. 

Map shows work zone will occupy area of the Eglinton roadway

Timing Read more »

December 122016

Overnight CCTV Investigations along Eglinton Avenue East

What Work is Taking Place?

Crews will be conducting CCTV investigations of the storm and sanitary sewer lines along Eglinton Avenue East. Crews will access all manholes in the roadway along Eglinton Avenue East between Midland Avenue and Laird Drive, along Transway Crescent at Kennedy Station and from approximately 50-100 meters north at all intersections to determine the condition of existing storm and sanitary lines. 

Hours of Work Read more »

Or, let us help you Experience Eglinton. Choose a category to explore the neighbourhood:

Syndicate content