Thank you for attending our Caledonia station open house on June 23, 2016.
For those of you who missed it, the presentation is here:
As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Read more »
Dear Neighbour:
As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive.For the tunnelled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.
On average, the tunnel boring machines each travel approximately 10-15 metres per day. TBMs are working approximately 16-20 metres below ground, but we sometimes hear from nearby residents who may experience noise and vibration from the TBMs as they pass through the area. Read more »
The Crosstown team appreciates the patience of our neighbours and local businesses while we work to build new rapid transit. In 2015, the project made significant progress and hit a number of key milestones. We would like to take this opportunity to reflect on the past year and provide a look ahead to how we expect the project to progress in 2016. Read more »
Starting in early January, a work crew will be seen conducting survey, locating utilities, and drilling boreholes to obtain additional information of sub-surface utilities and ground conditions near the future LRT Stations for Caledonia, Dufferin, Oakwood, Bathurst and Chaplin. Read more »
Dear Neighbour:
As you may know, the Eglinton Crosstown is a 19-kilometre light rail transit that includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunneled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.
On average, the tunnel boring machines each travel about 10 metres per day. TBMs are working about 20 metres below ground, but we do sometimes hear from nearby residents who may experience vibration from the TBMs as they pass through the area. Read more »
Dear Neighbour:
As you may know, the Eglinton Crosstown is a 19-kilometre light rail transit that includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunneled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.
On average, the tunnel boring machines each travel about 10 metres per day. TBMs are working about 20 metres below ground, but we do sometimes hear from nearby residents who may experience vibration from the TBMs as they pass through the area. Read more »
As you know, tunnelling continues on the Eglinton Crosstown Light Rail Transit (LRT) project as we build the underground portion of the future transit line.
The tunnel boring machines (TBMs) operate around the clock - 24 hours a day, seven days week. On average, they each travel about 10 metres per day. Our TBMs are working about 20 metres below ground, but we do sometimes hear from nearby residents who may experience vibration from the TBMs as they pass through the area. Read more »
Metrolinx is making progress on the Crosstown project. Construction of a launch shaft east of Brentcliffe Road is complete and assembly of two tunnel boring machines (TBMs) is nearing completion. Utility relocation and headwall construction along Eglinton Avenue East between Brentcliffe and Bayview started in January 2014. Some works along the road have been completed and others are progressing well. The Crosstown Team appreciates the patience of our neighbours while we work to build transit. Read more »
The Eglinton Crosstown Project is building the Eglinton Line, a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with a 10-kilometre underground tunnel in its central section. When it’s complete, the line will connect Mount Dennis in the west to Kennedy Road in the east, and will be up to 60% faster than bus service today. Read more »