What Work Is Taking Place?
On Tuesday, April 19, 2022, crews will perform watermain work at Cedarvale Station. A water shut-off is required to facilitate the work. The water shut-off will start at 11:00 p.m. for approximately six (6) hours. Water service will be restored upon completion of the work. Please carefully read the water shut-off details below.
Water Shut-off Details:
Update: Road Decking Removals at Bayview Avenue and Eglinton Avenue East
What Work is Taking Place? Read more »
What Work is Taking Place?
In early May 2022, crews at Oakwood Station will begin sidewalk restoration works on the north side of Eglinton Avenue West, east and west of the Main Entrance site (refer to map). This work will take place between 7:00 a.m. – 7:00 p.m. for approximately one (1) week. Short-term pedestrian rerouting may be required to complete this work.
As early as Saturday April 23, 2022, a new traffic configuration will be implemented at Mt Pleasant Road and Eglinton Avenue East. Traffic on Mt Pleasant Road will shift to the west side of the street and construction will move to the east side. As part of this work, the traffic bridge on the east side of Mt Pleasant Road will be removed.
Work is Taking Place?
As early as Monday, April 11, 2022, crews at Oakwood Station will install monitoring equipment on Eglinton Avenue West, west of Oakwood Avenue. Rolling lane closures are required to complete this work. Eglinton Avenue West will be reduced to one lane in each direction, while this work takes place. This work expected to take place between 9:00 a.m. – 4:00 p.m. for approximately four (4) days.
Notice of Power Outage at Fairbank Station
What Work is Taking Place?
On Tuesday, April 12, 2022, crews will be continuing overhead power cable installations at Fairbank Station. A power outage is required to facilitate this work. Power service will be restored upon completion of the work. Please carefully read the temporary power outage details below.
Power Outage Details: