Construction Updates

March 182018

Upcoming Traffic Changes at Kennedy Road and Eglinton Avenue East

What Work is Taking Place?

Starting as early as Thursday, March 22, 2018, crews will start support of excavation work, also known as shoring, for the future Kennedy Station. As part of these works traffic staging at the intersection of Kennedy Road and Eglinton Avenue East will be changing.   Read more »

March 162018

Lane Impacts and Driveway Work at Leaside Station


Work requiring the use of the eastbound lane between Bayview Avenue and 1750 Bayview Driveway will continue for the next one (1) to two (2) weeks. This work is required to support the completion of decking on the southwest corner.

Read more »

March 152018

Toronto Hydro Installation for Facility Services Building Construction at Eglinton Station

What Work is Taking Place?

As early as March 20, work will get underway to install new underground Toronto Hydro infrastructure that will replace the existing overhead cables, provide temporary power during construction of the Facility Services Building for the TTC Line 1 Subway system (pictured below) and new power connections for the same in the future. The existing overhead cables will be removed to facilitate the construction of the new building. Read more »

March 152018

Mining at Avenue Station - Both Station Entrances

What Work is Happening?

The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Avenue Station, are going to be “mined.” 

Excavation of the Main Entrance at Avenue Station is nearing completion and mining will begin soon. Read more »

March 132018

Toronto Hydro Relocation Work at Cedarvale Station

What Work is Taking Place?

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating a Toronto hydro infrastructure from underground ducting to overhead cables. The work will involve trenching and removing the existing duct banks, and installing new overhead hydro cables. Read more »

March 132018

75-Hour Weekend Work for GO Transit Improvements at Kennedy Station

Originally Published: March 13, 2018

Updated: March 15, 2018

Updated: March 16, 2018 Read more »

March 132018

Black Creek Drive Lane Closures

Updated March 13


March 132018

Overnight Water Site Service Connections at Eglinton Station

What Work is Taking Place?

In order to prepare for construction of Eglinton Station, crews have relocated water mains and sewers at the Yonge-Eglinton intersection to allow for piling and excavation works. In order to complete the next stage of the work, crews will be connecting the new temporary main with the existing site service connections. The following properties may lose water service during the connections:

20, 30, 40, and 50 Eglinton Avenue East


Hours of Work Read more »

Or, let us help you Experience Eglinton. Choose a category to explore the neighbourhood:

Syndicate content