Construction Updates

April 272018
April 262018

UPDATE: Pedestrian Route Changes at Leaside Station

ORIGINAL POST: APRIL 6, 2018

RE-ISSUE DATE: APRIL 19, 2018

RE-ISSUE DATE: APRIL 26, 2018

 

WHAT WORK IS TAKING PLACE? Read more »

April 262018
April 252018
April 242018

Mt. Pleasant Road Closure and Overnight Work: April 27 – 30, 2018 and Overnight Water Shut-off on Friday April 27

 

What Work is Taking Place?

Since April 14, crews have carried out weekend closures of Mt. Pleasant Road between Eglinton Ave E and Roehampton Ave to perform hydro utility relocation work. As part of this work, a watermain cut-and-cap will be performed, requiring a temporary water shut-off.  Read more »

April 202018

Large Tower Crane Delivery at Science Centre Station

Orignally Published: April 20, 2018

Updated: April 25, 2018

What Work is Taking Place?

On Saturday, April 28, 2018, a large tower crane will be delivered to Science Centre Station. The tower crane will be erected within the existing construction zone on Eglinton Avenue East, west of Don Mills Road.    Read more »

April 202018

Upcoming Works at Eglinton Station: Next Phase of Support of Excavation

What Work is Taking Place?

Support of excavation work, also known as shoring, has commenced to make way for the future Eglinton interchange station. This work will include pile installation, jet grouting and road deck installation. Shoring will be conducted in phases, beginning in the former TTC bus depot on the southeast corner of Yonge and Eglinton and along the south side of Eglinton Avenue between Duplex Avenue and Holly Street.  Read more »

April 192018

UPDATE: Pedestrian Route Changes at Leaside Station

ORIGINAL POST: APRIL 6, 2018

RE-ISSUE DATE: APRIL 19, 2018

 

WHAT WORK IS TAKING PLACE? Read more »