Crosstown

Construction Updates

November 202019

Upcoming Lane Closure Between Wynford Drive and Credit Union Drive for Oversized Delivery of Building Pieces

Upcoming Lane Closure Between Wynford Drive and Credit Union Drive for Oversized Delivery of Building Pieces

Friday November 22 – Sunday November 24, 2019

What Work is Taking Place? Read more »

November 202019

New Traffic Configuration at Rosemount Drive Road and Eglinton Avenue East

 

What Work is Taking Place

As early as Saturday November 30, 2019, a new traffic configuration will be implemented at Rosemount Drive and Eglinton Avenue East to facilitate construction of the future surface stops and guideway. Westbound traffic will be shifted north of the work zone. Left turns will remain prohibited at the Rosemount Drive Intersection. There will be no north-south through traffic on Rosemount Drive. 

The new traffic configuration will be implemented as early as November 30, 2019

  Read more »

November 152019

UPDATED: New Traffic Configuration at Kennedy Road and Eglinton Avenue East

Original Post: November 13, 2019

UPDATED on November 15, 2019

What Work is Taking Place

As early as Saturday, November 30, 2019, a new traffic configuration will be implemented at Kennedy Rd and Eglinton Avenue East to facilitate construction of the future Kennedy LRT Station and guideway. An additional southbound through lane on Kennedy Road at Eglinton Avenue East will be restored and the west crosswalk will be reinstated at the intersection. This traffic set up is expected to remain in place through spring 2020.   Read more »

November 132019

Upcoming Berwick Avenue Road Closures for TTC Line 1 Facility Service Building Construction - Friday November 15, 2019

 

What Work is Taking Place?

In 2019, crews have conducted a series of closures of Berwick Avenue between Duplex Avenue and Yonge Street to perform supporting construction activities for TTC’s Line 1 Subway Facility Services Building.  

The next closure is scheduled for Friday November 15, 2019.  During the closure, a large crane will be erected in the roadway and will be used to lift equipment into the work zone.  Read more »

November 122019

CONCRETE POURS ON EGLINTON AVENUE EAST EAST DON RIVER BRIDGE TO SLOANE AVENUE

ORIGINAL POSTING: NOVEMBER 7, 2019

UPDATED: NOVEMBER 12, 2019

CONCRETE POURS ON EGLINTON AVENUE EAST Read more »

November 112019

CONCRETE POUR ON EGLINTON AVENUE EAST WEST OF THE WYNFORD DRIVE BRIDGE

CONCRETE POUR ON EGLINTON AVENUE EAST

WEST OF THE WYNFORD DRIVE BRIDGE  Read more »

November 082019

Mid-Block Guideway Work at the East of Birchmount Road

 

What Work is Taking Place?

On Sunday November 3, 2019, Rosemount Drive will be closed north of Eglinton Avenue East for approximately six (6) weeks to facilitate guideway construction for the future Eglinton Crosstown LRT surface stops.  Guideway construction includes, cutting and removal of asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops. Read more »