November 272019

Update: Cross Passage 10 at Lillian Street

Original Post: November 5, 2019

Updated on November 27, 2019

Underground excavation continues in the tunnels below Eglinton Avenue East at Lillian Street. This work occurs on a 24- hour basis and is expected to be completed by February 2020. The excavation will create a connection corridor underground between the north tunnel and the south tunnel.

The dewatering system located on the southeast corner of Lillian Street that has been operating on a 24-hour basis since early 2019, will continue to operate on the surface until excavation is complete. Read more »

November 262019

Construction Notice: Traffic Configuration Change at Cedarvale Station - November 30

*Dates changed - Updated on November 28*

What Work is Taking Place? Read more »

November 262019

Construction Notice: Closure of Chaplin Crescent for Overnight Concrete Pour on Nov 28

*Updated on Nov 26 - This work has been rescheduled to Nov 28, due to inclement weather concerns* Read more »

November 262019

Temporary Lane Closures at Victoria Park Avenue

Temporary Lane Closures at Victoria Park Avenue

November 27 & 28 Read more »

November 202019

Line 1 Subway Closure for TTC Line 1 Facility Service Building Construction - November 30 – December 1, 2019

 

What Work is Taking Place?

Construction of a new Facility Service Building for TTC’s Line 1 Subway is underway at Berwick Avenue and Yonge Street.  Some of the work can only be safely performed while the subway is not operational.  Crews will work Friday November 29 through Monday December 2, 2019, to install plates on the track level, plumbing, hydro duct bank installation, strut installation and investigative work.   Read more »

November 202019

New Traffic Configuration at Rosemount Drive Road and Eglinton Avenue East

 

What Work is Taking Place

As early as Saturday November 30, 2019, a new traffic configuration will be implemented at Rosemount Drive and Eglinton Avenue East to facilitate construction of the future surface stops and guideway. Westbound traffic will be shifted north of the work zone. Left turns will remain prohibited at the Rosemount Drive Intersection. There will be no north-south through traffic on Rosemount Drive. 

The new traffic configuration will be implemented as early as November 30, 2019

  Read more »

November 202019

Upcoming Crane and Building Delivery of TPSS 11 - Monday November 25 – Thursday November 28, 2019

 

What Work is Taking Place

The Traction Power Substation 11 (TPSS 11) building will be delivered to Scarborough Nissan on Monday November 25, 2019. The TPSS 11 will be delivered in three oversized loads. Vehicles carrying the loads will travel southbound on Warden Avenue and continue eastbound on Civic Road. 

Traffic will be temporarily stopped south of Civic Road in both directions to accommodate the delivery. Read more »

November 202019

Upcoming Crane and Building Delivery of TPSS 11 - Monday November 25 – Thursday November 28, 2019

 

What Work is Taking Place

The Traction Power Substation 11 (TPSS 11) building will be delivered to Scarborough Nissan on Monday November 25, 2019. The TPSS 11 will be delivered in three oversized loads. Vehicles carrying the loads will travel southbound on Warden Avenue and continue eastbound on Civic Road. 

Traffic will be temporarily stopped south of Civic Road in both directions to accommodate the delivery. Read more »

November 202019

Upcoming Lane Closure Between Wynford Drive and Credit Union Drive for Oversized Delivery of Building Pieces

Upcoming Lane Closure Between Wynford Drive and Credit Union Drive for Oversized Delivery of Building Pieces

Friday November 22 – Sunday November 24, 2019

What Work is Taking Place? Read more »