August 072019

Overnight Watermain Work East of Bermondsey/Sloane

Overnight Watermain Work East of Bermondsey/Sloane

 

WHAT WORK IS TAKING PLACE? Read more »

August 072019

TRAFFIC CHANGE ON EGLINTON AVENUE EAST BETWEEN BRENTCLIFFE ROAD AND THE WEST DON RIVER BRIDGE

WHAT WORK IS TAKING PLACE?

A change in traffic alignment is expected to occur on Eglinton Avenue East between Brentcliffe Road and the West Don River Bridge as early as August 15, 2019. Eastbound and westbound traffic will be shifted to the north side of Eglinton Avenue East to accommodate the continued construction of the Brentcliffe Portal and the rehabilitation of the West Don River Bridge. Traffic will continue to be one lane in each direction. Read more »

August 062019
August 062019

Weekly Lane Reduction at Cedarvale Station for Geotechnical Work August – December 2019

What Work is Taking Place?

Starting Thursday, August 8th, crews will conduct a weekly closure of the eastbound curb lane of Eglinton Avenue West to perform geotechnical monitoring. Eglinton Avenue will be reduced to one lane in each direction between Winnett Avenue and Allen Road North every Tuesday from 12:00 p.m. – 3:30 p.m. through December 2019. Traffic control personnel and/or a Paid Duty Officer will be present while this work takes place.

Details Read more »

August 012019
August 012019

UPDATED: OVERNIGHT WATERMAIN RELOCATION AT SADDLE RIDGE DRIVE

What Work is Taking Place?

As part of the continued construction of the Eglinton Crosstown LRT, crews will be relocating the watermain along Eglinton Avenue East at Saddle Ridge Drive. Relocation is required for road widening activities as well as construction of a new retaining wall along Eglinton Avenue East in front of the Saddle Ridge Drive cul-de-sac. Work will occur overnight and is expected to begin as early as 6:00p.m. on Tuesday, August 6, 2019 and continue for up to four (4) nights. Read more »

August 012019

Bathurst and Eglinton Overnight Intersection Closure - August 23 & 24, 2019

What Work is Taking Place?

The intersection of Bathurst Street and Eglinton Avenue West will be closed while crews complete a large concrete pour at Forest Hill Station. The concrete will form part of the future roof of the station.  The closure will take place on Friday, August 23, 2019 and continue into the following day.  The concrete pour will take approximately 18 hours to complete. Once the work is complete, the intersection will re-open.  Read more »

July 312019

Lane Reduction for Overnight Concrete Pour at Forest Hill Station Friday August 2, 2019

On Friday August 2, 2019 beginning at 3:00 a.m. crews will perform a concrete pour at Forest Hill Station.  The concrete will form part of the future station roof.  Lane reductions will be in effect for concrete truck staging.  This is not a full intersection closure.  Trucks will stage in the eastbound curb lane of Eglinton Avenue between Chiltern Hill Road and Menin Road and in the westbound curb lane between Bathurst Street and Mayfair Avenue.  The concrete pour will take approximately 12 hours to complete. Read more »

July 312019

Concrete Pour at Cedarvale Station Tuesday, August 6, 2019

On Tuesday, August 6, 2019, crews will perform a concrete pour in the work zone south of the Eglinton West subway station. The concrete will form part of a permanent station structure in the west side of the TTC box.  One concrete pump will be set up within the work zone, and concrete trucks will stage on the east side of Allen Road southbound while this work takes place. Traffic control personnel and/or a Paid Duty Officer will be present while this work takes place. Read more »