May 122020

Concrete Pour at Laird Station

CONCRETE POUR AT LAIRD STATION

May 15, 2020 Read more »

May 112020

Concrete Pour at Cedarvale Station - Wednesday, May 13, 2020

What Work is Taking Place?

As early as Wednesday, May 13, 2020, crews will perform a concrete pour within the work zone south of Eglinton West subway station. To ensure the integrity and continuity of the pour, work will begin as early as 5:30 a.m. and take approximately eight (8) hours to complete. Read more »

May 082020

UPDATE:Concrete Pour at Avenue Station: May 11, 2020

What Work is Taking Place? 

As early as May 11, 2020 crews will perform a concrete pour at the main entrance of Avenue Station. The concrete will form one of the permanent station structures underground. To safely carry out the works, westbound traffic on Eglinton Avenue West will be reduced to one lane at the Main Entrance. The pour will begin at 10:00 a.m. and take approximately five (5) hours to complete.  After each pour is complete, the lane will re-open.

  Read more »

May 082020

UPDATED: Shelter Installation at Eastbound Pharmacy Stop until May 15, 2020

 

Original Post: April 22, 2020

Last updated: May 8, 2020

 

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install the final two permanent shelters at Pharmacy Avenue and Eglinton Avenue East at the south platform. Installation will begin as early as April 27, 2020 through to May 15, 2020. Lane closures will be required for this work (depicted below). 

Read more »