Orignally Published: April 20, 2018
Updated: April 25, 2018
On Saturday, April 28, 2018, a large tower crane will be delivered to Science Centre Station. The tower crane will be erected within the existing construction zone on Eglinton Avenue East, west of Don Mills Road. Read more »
Crews are working to replace an existing watermain north of Eglinton Avenue East within the existing work zone at the northeast corner of Don Mills Road and Eglinton Avenue East. This work supports the upgrade of existing water infrastructure around the future Science Centre Station. Read more »
The construction liaison committee meeting of Brentcliffe - Victoria Park was held on April 5, 2018. You can see the presentation here:
Thank you for attending the open house about Laird Station to West At-Grade (Sunnybrook - O'Connor Stops) on March 28, 2018.
For those of you who missed it, the presentation is here: Read more »
As our constructors get ready to ramp up construction activity at the surface section of the Eglinton Crosstown LRT project, clearing, grubbing, and pruning and protection activity continues as part of preparatory work. This activity commenced two years ago and is done on an ongoing, as-needed basis to support the construction of the Eglinton Crosstown Light Rail Transit Project (ECLRT). All works will be carried out with the approvals and cooperation of the responsible authority. Read more »
What Work is Taking Place?
Ongoing road maintenance continues around the Don Mills Road and Eglinton Avenue East intersection. The rebuilding of catch basins on Eglinton Avenue East between the DVP and Don Mills Road will start on Monday, March 12, 2018 for approximately one week.
To minimize traffic disruption for the community, transit users and local businesses, this work is being done overnight.
Hours of Work Read more »
Crews are working to replace an existing watermain north of Eglinton Avenue East within the existing work zone at the northeast corner of Don Mills Road and Eglinton Avenue East. This work supports the upgrade of existing water infrastructure around the future Science Centre Station.
Starting in mid-March for approximately three (3) weeks, work to connect the new watermain section to the existing infrastructure will take place. During these works, residents in the catchment area may experience lower than normal water pressure. Read more »
The construction liaison committee meeting of Brentcliffe - Victoria Park was held on March 1, 2018. You can see the presentation here:
Crews will be drilling piles within the Don Mills Road and Eglinton Avenue East intersection as part of the Support of Excavation work at the future Science Centre Station.
Due to the location of the piles and in an effort to minimize disruption to local traffic and commuters work will be performed overnight on Wednesday, February 28, 2018 from 8:00 p.m. to 5:00 a.m. Thursday morning. The intersection will be restored in advance of morning rush hour. Read more »
What Work is Taking Place? Read more »
Experience Eglinton by street: