ORIGINAL POST: OCTOBER 5, 2018
Upcoming Traffic Changes at Don Mills and Eglinton
What Work is Taking Place? Read more »
The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here:
As part of the ongoing watermain upgrades for the future Science Centre Station, crews will be conducting overnight watermain relocation works at the intersection of Eglinton Avenue East and Don Mills Road.
In an effort to minimize disruption and to protect the safety of the local community and commuters, work will be performed overnight beginning as early as Sunday August 26, 2018 and will continue for approximately five (5) nights. Read more »
The construction liaison committee meeting of Brentcliffe - Victoria Park for June 14, 2018. You can see the presentation here:
As part of the ongoing storm water and sanitary utility upgrades for the future Science Centre Station, crews will be completing the connection of the new infrastructure to the existing at the northwest corner of Don Mills Road and Eglinton Avenue East. Read more »
As part of ongoing utility relocation work for the future Science Centre Station, crews will be conducting hydro infrastructure work in the vicinity of the Don Mills Road and Eglinton Avenue East intersection, beginning as soon as Wednesday, June 13, 2018. Ongoing hydro infrastructure upgrades support construction of the Eglinton Crosstown LRT. Read more »
Originally Published: June 7, 2018
Updated: June 11, 2018
Updated: June 22, 2018
Updated: June 28, 2018
Updated: July 03, 2018
As part of the continued support of excavation works and utility relocation works for the future Science Centre Station, traffic staging at the intersection of Don Mills Road and Eglinton Avenue East will be changing. Read more »
Crews continue to connect the new sanitary sewer to the existing sanitary sewer infrastructure, as part of infrastructure upgrade for the new Science Centre Station. Work commenced as early as Tuesday, May 22, 2018 and was estimated to take approximately two (2) weeks to complete. However, crews have encountered some unforeseen issues. Read more »
Crews will connect the new sanitary sewer to the existing sanitary sewer infrastructure, as part of infrastructure upgrade for the new Science Centre Station, beginning as early as Tuesday, May 22, 2018. Work is expected to take approximately two (2) weeks to complete* between 8:00 PM and 6:00 AM. Read more »
The presentation for the construction liaison committee meeting of Brentcliffe - Victoria Park for the month of May 2018 can be viewed here:
Experience Eglinton by street: