Crosstown

What's New?

Syndicate content
 
January 22 2019

Updated: Resumption of Overnight Wet Utilities Work at Forest Hill Station January 24, 2019

What Work is Taking Place?

Crews have been completing overnight wet utility and hydro utility installation work at Forest Hill Station since September 2018; this work will continue through until mid-February 2019. 95% of all utilities relocation and installation work at Forest Hill Station have been completed.

Resuming January 24, 2019, overnight water main chamber construction will commence on Eglinton Avenue, east of Bathurst Street. Traffic in the vicinity of the work area will be reduced to one (1) lane only, alternating in each direction.  Read more »

January 22 2019

Overnight Closure of Temporary Access Road for Utility Work

WHAT WORK IS TAKING PLACE?

To facilitate the ongoing utility relocation at the future Kennedy Station, there will be overnight closures of the Temporary Access Road. Starting as early as Tuesday January 22, 2019 and lasting for approximately three (3) nights. Crews will sleeving out switches on the hydro lines at the temporary access road.

Read more »

January 22 2019

Reopening of North End of Existing East Platform at Kennedy GO Station

What Work is Taking Place?

Kennedy Station is an interchange station with connections to the GO Transit Stouffville Line, the TTC Scarborough RT, the TTC Bloor-Danforth subway, and a TTC bus terminal. Construction of the Eglinton Crosstown LRT Kennedy Station will include upgrades to the existing Kennedy Station infrastructure. Read more »

January 22 2019

Traffic Deck Replacement at Eglinton West Subway Station (Cedarvale)

What Work is Taking Place?

  • Crews will be replacing the road decking on the north side of Eglinton Avenue from Park Hill Road to Allen Road South.

Hours of Work Read more »

January 18 2019

Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road.

Telecom work has been extended until the Spring 2019.

Read more »

January 18 2019

Overnight Traffic Change at Forest Hill Station

What Work is Taking Place? 

As early as January 20, 2019, a new traffic configuration will be implemented at Forest Hill Station.  Traffic on Bathurst Street will be shifted to the east side, and traffic on Eglinton Avenue will remain on the south.  This configuration will be in place for approximately three weeks until early February 2019.  Pile installation, excavation and utilities work will continue through winter 2019. Read more »

January 16 2019

Overnight Traffic Change at Forest Hill Station

Originally Published: January 7, 2019

Updated: January 16, 2019 

What Work Is Taking Place? Read more »