Construction Liaison Committee of Pharmacy to Kennedy was held on March 31, 2020. You can see the presentation here:
Last update: January 9, 2020
Updated on March 27, 2020
What Work is Taking Place
As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews continue work with stage two at Massey Creek. There will be a partial driveway closure to the driveway access for 2239 and 2243 Eglinton Avenue East. The partial driveway restriction will be extended through July 31 in order to carry out the remaining work safely. Access to the properties will be maintained at all times. Read more »
What Work is Taking Place
As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended until April 1, 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through traffic will be prohibited for the duration of the work.
Work continues at the east wing-wall of the creek and includes excavation, concrete works, removal of form work and backfilling. Read more »
WHAT WORK IS TAKING PLACE
As part of the ongoing construction of the Eglinton Crosstown LRT, crews continue rehabilitation and reconstruction of the Massey Creek culvert at the Eglinton Avenue East and Rosemount Drive intersection.
Starting February 4, 2020, for a maximum period of three (3) weeks, crews will work extended hours to accelerate construction. Construction activities will include excavation, welding, rebar, formwork and concrete works. Read more »
The construction liaison committee meeting of Pharmacy to Kennedy was held on January 28, 2020. You can see the presentation here:
Original Post: November 15, 2019
Updated: January 6, 2020
What Work is Taking Place
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting mid-block guideway and stop construction between Victoria Park Avenue and Ionview Road, for approximately eight (8) months through spring 2020. Read more »
What Work is Taking Place
As part of the ongoing works to replace the existing culvert at Massey Creek, a new traffic configuration will be implemented at Rosemount Drive and Eglinton Avenue East as early as Thursday January 2, 2020. Rosemount Drive will be closed north of Eglinton Avenue East and north-south through traffic will be prohibited for the duration of the work.
Work includes excavation, concrete works, shoring installation and backfilling. Read more »
The construction liaison committee meeting of Pharmacy to Kennedy was held on November 26, 2019. You can see the presentation here:
What Work is Taking Place
As early as Saturday November 30, 2019, a new traffic configuration will be implemented at Rosemount Drive and Eglinton Avenue East to facilitate construction of the future surface stops and guideway. Westbound traffic will be shifted north of the work zone. Left turns will remain prohibited at the Rosemount Drive Intersection. There will be no north-south through traffic on Rosemount Drive.
The new traffic configuration will be implemented as early as November 30, 2019
What Work is Taking Place?
On Sunday November 3, 2019, Rosemount Drive will be closed north of Eglinton Avenue East for approximately six (6) weeks to facilitate guideway construction for the future Eglinton Crosstown LRT surface stops. Guideway construction includes, cutting and removal of asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops. Read more »