Crosstown

Ionview Road

February 272019

East At-Grade Town Hall Meeting

Our town halls provide information on construction impacts on Eglinton Avenue East between Credit Union Drive to Ionview Road feature detailed project maps and imagery. You can see the presentation here:

Read more »

February 252019

Overnight Invert Concrete Pours at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road on Thursday, February 28, 2019 from 4:00 a.m. until 4:00 p.m. To facilitate this delivery, concrete trucks will be arriving to the site from the east and west Eglinton Avenue East.

Stage 1 Read more »

January 312019

Updated: Hydro Utility Relocation between Birchmount Road to Kennedy Road

What Work is Taking Place?

In support of construction of the future Crosstown Light Rail Transit, crews will continue relocation and upgrading of existing overhead and underground utilities between Birchmount Road and Kennedy Road. Work began in June of 2017 and will continue for another six (6) months. Read more »

January 312019

Revised: Massey Creek Culvert Work Begins

Latest Update: March 18, 2019

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews will be replacing the existing culvert at Massey Creek. Work began as early as late February 2019 and will last for approximately nine (9) months. The creek is located at the signalized intersection of Eglinton Avenue East and Rosemount Drive. Read more »

January 292019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on January 29, 2019. You can see the presentation here:

Read more »

December 132018

Overnight Invert Concrete Pours at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road on Friday, December 14, 2018 from 4:00 a.m. until 10:00 a.m. To facilitate this delivery, concrete trucks will be arriving to the site west of Ionview Road. Read more »

December 042018

Sidewalk Closure at Rosemount Drive and Eglinton Avenue East to Support Subsurface Utility Investigation Work

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting subsurface utility investigation along Eglinton Avenue East between Birchmount Road and Rosemount Drive.

Work began as early as November 26th. There will be sidewalk closure on the north side of Eglinton Avenue East near 2306 Eglinton Avenue East in order to safely carry out the work. Read more »

December 042018

Investigation of Underground Utilities between Birchmount Road and Rosemount Drive

What Work is Taking Place?

In support of construction of the future At-Grade stops, crews will be conducting subsurface utility engineering (SUE) investigation work along Eglinton Avenue East between Birchmount Road and Rosemount Drive.

Crews will drill bore holes and use a hydro-vacuum truck within the City’s right-of-way and roadway to determine the location and depth of existing underground utilities for design purposes. Read more »

December 032018

Overnight Invert Concrete Pours at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road as early as Friday, December 7, 2018 from 4:00 a.m. until 10:00 a.m. To facilitate this delivery, concrete trucks will be arriving to the site west of Ionview Road.

Read more »

November 302018

Wet Utility Upgrades along Surface Section of the Eglinton Crosstown LRT: Birchmount Road to Rosemount Drive

What Work is Taking Place?

In support of construction of the future At Grade stops, crews will be conducting wet utilities relocation work along Eglinton Avenue East between Birchmount Road and Rosemount Drive. Starting as early as December 3, 2018 and lasting approximately four (4) months, crews will install new pipes, and replace manholes and catch basins. The work will be conducted in stages.

Stage 1 Read more »