Crosstown

Ionview Road

June 272018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committe meeting of Pharmacy to Kennedy was held on June 26, 2018. You can see the presentation here:

May 302018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on May 29, 2018. You can see the presentation here:

Download the presentation

May 252018

UPDATE: Watermain, Storm and Sanitary Relocation between Ionview Road and Rosemount Drive

Originally Published: May 25, 2018

Updated: May 28, 2018

Updated: May 29, 2018

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews continue to upgrade and relocate wet utilities along Eglinton Ave between east of Birchmount Road to west of Midland Avenue, including the North Service Road. Read more »

May 172018

EXTENDED: Temporary Closure of Ionview Road

What Work is Taking Place?

Storm and sanitary utilities relocation work continues at Ionview Road and Eglinton Avenue East following temporary closure of Ionview Road at Eglinton Avenue East on Monday, May 7th, 2018. This also involves executing an east-west crossing at Ionview Road. The work is part of a larger upgrade and relocation of utilities as part of the Eglinton Crosstown LRT. Read more »

April 252018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on April 24, 2018. You can see the presentation here: 

April 122018

East Open House: East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station

Thank you for attending the open house about East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station on April 11, 2018.

For those of you who missed it, the presentation is here: Read more »

March 282018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on March 27, 2018. You can see the presentation here: 

March 132018

Temporary Closure of Ionview Road

Originally Published: March 13, 2018

Updated: April 8, 2018

Updated: April 20, 2018

Updated: May 03, 2018

Updated: May 07, 2018

Updated: May 17, 2018

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews will be relocating storm and sanitary utilities in the vicinity of Ionview Road and Eglinton Avenue East, including performing an east-west crossing across Ionview Road. Read more »

February 282018

Pharmacy - Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on February 27, 2018. You can see the presentation here: 

Read more »

January 312018

Pharmacy - Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on January 30, 2018. You can see the presentation here:

Or, let us help you Experience Eglinton. Choose a category to explore the neighbourhood:

Syndicate content