What Work is Taking Place?
Crews will begin the relocation and upgrading of an existing watermain on the north and south sides of Eglinton Avenue East, the North Service Road and the South Service Road from Kennedy Road to approximately west of Midland Avenue. In an effort to minimize disruption to local traffic and commuters, work will be performed in stages. Read more »
Thank you for attending the open house about Kennedy Station and East At-Grade (Pharmacy Stop to Ionview Stop) on December 5, 2017.
For those of you who missed it, the presentation is here: Read more »
Originally Published: November 10, 2017
Updated: December 08, 2017
Updated: January 03, 2018
Kennedy Station will be the terminal station at the eastern end of the Eglinton Crosstown LRT line. Kennedy Station is an interchange station with connections to the GO Transit Stouffville Line, the TTC Scarborough RT, the TTC Bloor-Danforth subway, and a TTC bus terminal. Construction of the Eglinton Crosstown LRT Kennedy Station will include upgrades to the existing Kennedy Station infrastructure. Read more »
Updated: November 6, 2017
Original Post: October 20, 2017
What Work is Taking Place?
Crews will remove existing traffic signals and install temporary traffic signals on Eglinton Avenue East between Leslie Street and Kennedy Road, to make way for the construction of future surface stops for the Eglinton Crosstown LRT.
Timing Read more »
Beginning as early as Monday, November 6, 2017 for approximately four (4) weeks, driveways at 2360 Eglinton Avenue East will be modified to support construction of the Crosstown LRT. Work will be done in two stages, each stage lasting approximately two (2) weeks.
Please see image below showing changes to access to 2360 Eglinton Avenue East during Stage 1 of this work.
What Work is Taking Place? Read more »
Originally Issued: October 27, 2017
Updated and Reissued: November 1, 2017
What Work is Taking Place? Read more »
What Work is Taking Place?
Crews will remove existing traffic signals and install temporary traffic signals on Eglinton Avenue East between Leslie Street and Kennedy Road, to make way for the construction of future surface stops for the Eglinton Crosstown LRT.
Timing Read more »
What Work is Taking Place?
As part of the ongoing work to construct Kennedy Station, crews will install temporary light poles and lines in the South Parking Lot starting as early as October 11, 2017. The work will be performed overnight in an effort to minimize disruption to the public and transit users.
Hours of Work Read more »
Updated: September 28, 2017
Original Issue Date: May 10, 2017
What Work is Taking Place?
As part of ongoing preparatory works, crews will begin the process of removing street furniture across the Eglinton Avenue East corridor between Leslie Street and Midland Avenue. Read more »
The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on September 26, 2017. You can see the presentation here: Read more »
Experience Eglinton by street: