Preliminary Notice to Businesses and Residents: Upcoming Power Outage Between Birchmount and Kennedy

What Work is Taking Place?

Since June 2017, crews have been upgrading and relocating existing hydro utilities in the area located just west of Birchmount Road to Kennedy Road in the vicinity of Eglinton Avenue East. To complete this work, a Hydro outage is required.

Hours of Work Read more »

September 152017

Upcoming: North Entrance Closure and Demolition at Kennedy Station in Fall 2017

We have been busy building you the new 19-kilometre Eglinton Crosstown light rail transit (LRT) line!

This has involved lots of moving parts — excavations at future stations, relocating and upgrading utilities, road widening, and center-medians removal work for future stops.

Now we are working at the eastern end of the Crosstown LRT line at Kennedy Station — a future interchange station (pictured below). Read more »

August 292017

Pedestrian Safety near Construction Sites

The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.

Read more »

August 292017

Parking Lot Reductions and Associated Works at Kennedy Station

What Work is Taking Place?

Parking will be displaced in the East and South Parking Lots at Kennedy Station to facilitate construction of the Kennedy Station. Works include: Read more »

August 112017

Toronto Hydro-Electric System Limited (THESL) Relocation Work at Kennedy Station

What Work is Taking Place?
Crews will relocate and upgrade existing overhead hydro utilities between the West Service Roads to the East Service Roads of Eglinton Ave East in preparation for construction of the Kennedy Portal and the Kennedy LRT Station.
July 262017

Pharmacy - Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on July 25, 2017. You can see the presentation here:

Download the presentation

July 142017

Median Removals on Eglinton Avenue East for Surface Stops

The surface section of the Eglinton Crosstown LRT will run down the centre of Eglinton Avenue East in dedicated transit lanes at street level. To prepare for the construction of the surface section, crews are working to get the roadway ready.

Setting up the construction work zones in the roadway will require changes to how car and truck, bus, and pedestrian traffic flows along Eglinton Avenue East and the associated intersections where future stops will be located. To conduct this work safely lane reductions will be required. Read more »

July 132017

Re-issue: Telecommunication Utilities Relocation: Birchmount Road to Treverton Drive

What Work is Taking Place?

• Crews will begin relocation of existing telecommunication lines along Eglinton Avenue East, between Birchmount Road and Treverton Drive.

• Telecommunication lines within utility chambers as well within pre-existing duct banks will be relocated in preparation for station construction.

• All work conducted during this phase will occur within the public boulevards.

Read more »