Construction Liaison Committee of Pharmacy to Kennedy was held on September 29, 2020. You can see the presentation here:
Construction Liaison Committee of Pharmacy to Kennedy was held on July 28, 2020. You can see the presentation here:
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Hakimi Lebovic Stop south platform. Installation will begin as early as July 9, 2020 for approximately three (3) days. Daily lane closures will be required for this work.
Hours of Work
• Shelter installation will begin as early as July 9, 2020 for a period of three (3) days. Read more »
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Hakimi Lebovic Stop north platform. Installation will begin as early as June 24, 2020, lane closures will be in place for approximately one (1) week.
Hours of Work
• Shelter installation will begin as early as June 24, 2020 for a period of one (1) week. Read more »
Construction Liaison Committee of Pharmacy to Kennedy was held on May 26, 2020. You can see the presentation here:
What Work is Taking Place
As part of the construction of the future Hakimi Lebovic Stop, crews will be constructing stop platforms at the Hakimi and Lebovic Avenue and Eglinton Avenue East intersection.
To accommodate these activities, eastbound and westbound TTC bus stops will be relocated at the intersection (depicted below) beginning May 25, 2020 for a period of eight (8) weeks.
Hours of Work Read more »
Experience Eglinton by street: