As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews continue with Bell infrastructure relocation work along Eglinton Avenue East between Pharmacy Avenue and Warden Avenue. Read more »
Crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road, as part of construction of the future surface section for the Eglinton Crosstown LRT.
Telecom work commenced in February and has been extended until the end of the year (Fall/Winter 2018).
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting Bell infrastructure relocation work along Eglinton Avenue East between Pharmacy Avenue and Warden Avenue. Read more »
The construction liaison committee meeting of Pharmacy to Kennedy was held on October 30, 2018. You can see the presentation here:
The construction liaison committee meeting of Pharmacy to Kennedy was held on September 25, 2018. You can see the presentation here:
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting traffic changes in order to accommodate road widening, upgrading and relocating wet utilities and dry utilities along Victoria Park Avenue to Birchmount Road starting as early as Friday, September 21st.
Preparatory work for the reconfiguration will take place as early as Friday, September 21, 2018 starting at 7:00 PM and ending Monday, September 24, 2018 at 6:00 AM. Read more »
Originally Published: September 14, 2018
Updated: September 17, 2018
Expect to see new traffic changes between Victoria Park and Birchmount beginning less than a week from today — as early as Friday, September 21, 2018. Read more »
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be upgrading and relocating wet utilities in the center of Eglinton Avenue East between Victoria Park Avenue and Birchmount Road starting as early as Monday, August 20th, 2018. Read more »
The construction liaison committe meeting of Pharmacy to Kennedy was held on June 26, 2018. You can see the presentation here:
What Work is Taking Place?
The Eglinton roadway is changing as work continues to prepare for the construction of the surface section of the Eglinton Crosstown LRT that will run down the centre of Eglinton Avenue East in dedicated transit lanes at street level.
Setting up the construction work zones in the roadway will require changes to how car and truck, bus, and pedestrian traffic flows along Eglinton Avenue East and the associated intersections where future stops will be located. Read more »
Experience Eglinton by street: