What Work is Taking Place?
Crews will be pouring the concrete foundation for the Brentcliffe Portal. Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 5:00 a.m. in order to complete the pour during daytime hours, reducing impact to traffic in the area. Read more »
The construction liaison committee meeting of Brentcliffe - Victoria Park was held on October 5, 2017. You can see the presentation here:
Updated: September 28, 2017
Original Issue Date: May 10, 2017
What Work is Taking Place?
As part of ongoing preparatory works, crews will begin the process of removing street furniture across the Eglinton Avenue East corridor between Leslie Street and Midland Avenue. Read more »
What Work is Taking Place?
Crews will be pouring the concrete foundation for the Brentcliffe Portal. Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 4:00 a.m. in order to complete the pour during daytime hours, reducing impact to traffic in the area. Read more »
The construction liaison committee meeting of Brentcliffe - Victoria Park was held on September 7, 2017. You can see the presentation here:
The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.
What Work is Taking Place?
Crews will be pouring the concrete foundation for the Brentcliffe Portal. Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 3:00 a.m. in order to complete the pour during daytime hours, reducing impact to traffic in the area. Read more »
The construction liaison committee meeting of Brentcliffe - Victoria Park was held on July 13, 2017. You can see the presentation here:
The surface section of the Eglinton Crosstown LRT will run down the centre of Eglinton Avenue East in dedicated transit lanes at street level. To prepare for the construction of the surface section, crews are working to get the roadway ready.
Setting up the construction work zones in the roadway will require changes to how car and truck, bus, and pedestrian traffic flows along Eglinton Avenue East and the associated intersections where future stops will be located. To conduct this work safely lane reductions will be required. Read more »
Experience Eglinton by street: