November 13 2019

Upcoming Berwick Avenue Road Closures for TTC Line 1 Facility Service Building Construction - Friday November 15, 2019

 

What Work is Taking Place?

In 2019, crews have conducted a series of closures of Berwick Avenue between Duplex Avenue and Yonge Street to perform supporting construction activities for TTC’s Line 1 Subway Facility Services Building.  

The next closure is scheduled for Friday November 15, 2019.  During the closure, a large crane will be erected in the roadway and will be used to lift equipment into the work zone.  Read more »

November 13 2019

New Traffic Configuration at Kennedy Road and Eglinton Avenue East

 

What Work is Taking Place

As early as Monday, November 25, 2019, a new traffic configuration will be implemented at Kennedy Rd and Eglinton Avenue East to facilitate construction of the future Kennedy LRT Station and guideway. An additional southbound through lane on Kennedy Road at Eglinton Avenue East will be restored and the west crosswalk will be reinstated at the intersection. This traffic set up is expected to remain in place through spring 2020.   Read more »

November 12 2019

CONCRETE POURS ON EGLINTON AVENUE EAST EAST DON RIVER BRIDGE TO SLOANE AVENUE

ORIGINAL POSTING: NOVEMBER 7, 2019

UPDATED: NOVEMBER 12, 2019

CONCRETE POURS ON EGLINTON AVENUE EAST Read more »

November 11 2019

Decking Repair Continues at Leaside Station

 

Decking Repair Continues at Leaside Station Read more »

Categories:
November 11 2019

CONCRETE POUR ON EGLINTON AVENUE EAST WEST OF THE WYNFORD DRIVE BRIDGE

CONCRETE POUR ON EGLINTON AVENUE EAST

WEST OF THE WYNFORD DRIVE BRIDGE  Read more »

November 08 2019

Mid-Block Guideway Work at the East of Birchmount Road

 

What Work is Taking Place?

On Sunday November 3, 2019, Rosemount Drive will be closed north of Eglinton Avenue East for approximately six (6) weeks to facilitate guideway construction for the future Eglinton Crosstown LRT surface stops.  Guideway construction includes, cutting and removal of asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops. Read more »

November 07 2019

Laneway Closure for Overnight Concrete Pour at Forest Hill Station - Nov 8, 2019

On Friday November 8, 2019 beginning at 4:00 a.m. crews will close the Hilltop Road-Bathurst Street laneway behind the Forest Hill Station Secondary Entrance to conduct a concrete pour. The concrete will form the exterior wall of the Secondary Entrance. The pour is one of a series of concrete pours that will take place in 2019 to construct the Secondary Entrance. The pedestrian walkway around the Secondary Entrance site will be closed while the pour takes place. Once the pour is complete, the pedestrian walkway around the Secondary Entrance site will re-open. Read more »

November 07 2019

Chaplin & Avenue Construction Liaison Committee Meeting - Nov 6, 2019

The construction liaison committee meeting of Chaplin & Avenue was held on November 6, 2019. You can view the presentation here:

November 07 2019

Traffic Improvement at Don Mills Road and Eglinton Avenue East

ORIGINAL POSTING: SEPTEMBER 25, 2019

UPDATED: NOVEMBER 7, 2019 Read more »