Lane Reduction for Escalator Delivery at Caledonia Station - September 9, 2020

 

What Work is Taking Place?

On Wednesday September 9, the final large escalators will be delivered to Caledonia station. During this activity, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 6:00am and last for approximately 12 hours.

 

What to Expect

September 04 2020

Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - September 8, 2020

 

 

What Work is Taking Place?

As early as Tuesday September 8, 2020, crews at Mount Pleasant Station will perform a concrete pour within the work zone of the north side of Eglinton Avenue East, west of Mount Pleasant Road. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 5:00 a.m. and take approximately eighteen (18) hours to complete. Read more »

September 04 2020

Berwick Road Closure for Concrete Pour - Tuesday September 8, 2020

 

 

What Work Is Taking Place?

On Tuesday September 8, 2020, Berwick Avenue will be closed at Yonge Street while a concrete pour will be carried out at the Berwick Portal site.  The concrete will form part of the portal foundation.  A concrete pump will be placed on Berwick Avenue and several concrete trucks will enter the site each hour.

 

What to Expect Read more »

September 04 2020

Berwick Road Closure for Concrete Pour - Tuesday September 8, 2020

 

 

 

What Work Is Taking Place?

On Tuesday September 8, 2020, Berwick Avenue will be closed at Yonge Street while a concrete pour will be carried out at the Berwick Portal site.  The concrete will form part of the portal foundation.  A concrete pump will be placed on Berwick Avenue and several concrete trucks will enter the site each hour.

 

What to Expect Read more »

September 03 2020

Update: Extended Construction Hours for Deep Excavation at Eglinton Station

 

Original Post; June 29, 2020

Updated on September 3, 2020

 

What Work is Taking Place?

Since late 2018, crews have been working extended construction hours to complete deep excavation of the future Eglinton Station.  In spring 2020, underpinning of TTC’s Eglinton Station box was completed.  The TTC box is now fully supported and deep excavation continues safely underneath. Read more »

September 02 2020

UPDATED: Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - September 3, 2020

 

Original Post: August 31, 2020

Updated on September 2, 2020

 

What Work is Taking Place?

As early as Thursday September 3, 2020, crews at Mount Pleasant Station will perform a concrete pour within the  Secondary Entrance site. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 6:00 a.m. and take approximately twelve (12) hours to complete. Read more »