September 25 2020

UPDATED: Notice of Planned Water Shut-off and Overnight Watermain Connection Work at Mount Pleasant Station

Original Post: September 22, 2020

Updated: September 23 & 25, 2020

 

 

What Work is Taking Place? Read more »

September 25 2020

Updated: Extended Hours at Laird Station (24 hour work) - September 30, 2020

What Work is Taking Place?

As early as September 30, 2020, permanent works at the Main Entrance will take place 24 hours a day, Monday through Friday for approximately five (5) weeks. The current extended hours (6:00 a.m. -1:00 a.m.) at both entrance shafts and in the tunnels, will continue through to the end of the year.

September 24 2020
September 23 2020

Late Night Concrete Pour at Birchmount Road and Eglinton Avenue East - September 24, 2020

 

 

What Work is Taking Place?

On September 24, 2020, crews will perform a late-night concrete pour on Eglinton Avenue East, West of Birchmount Road. The concrete will form the plinths that will support the future tracks of the Eglinton Crosstown LRT.  The pour will take place between the hours of 10:00 p.m. and 3:00 a.m.  Read more »

September 18 2020

Avenue & Chaplin CLC - Presentation Deck - September 9, 2020

Construction Liaison Committee of Avenue & Chaplin was held on September 9, 2020. You can see the presentation here.

Read more »

September 18 2020

Sidewalk Restoration Works at Hillsdale Avenue and Yonge Street - September 21, 2020

What Work is Taking Place?

On Monday September 21, 2020, sidewalk and curb restoration works will begin on the southside of Hillsdale Avenue between Duplex Avenue and Yonge Street. As part of this work, part of the existing sidewalk and roadway will be removed. Concrete and asphalt will be used to construct the new sidewalk and curbs. Read more »