September 01 2022

Update: Hydro Pole Installations at Avenue Station - August 15, 2022

What Work is Taking Place?

Crews at Avenue Station are currently installing hydro poles on the north side of Eglinton Avenue West. As early as Monday, August 15, 2022, hydro pole installations will begin on the south side of Eglinton Avenue West.

August 30 2022

TTC Line 1 Closures for Eglinton Crosstown LRT Construction Work - September 10-September 11th, 2022

What Work Is Taking Place?

TTC’s Line 1 subway will be closed between Lawrence and St. Clair stations from Saturday, September 10 – Sunday, September 11, 2022, to facilitate construction activities for the Eglinton Crosstown LRT. Work will take place on a 24-hour basis from Saturday, September 10 – Sunday, September 11, 2022 . Berwick Avenue will remain open while this work takes place.

What to Expect Read more »

August 29 2022

Update: Pedestrian Route Change at Chaplin Station August 26, 2022

What Work is Taking Place?

As early as Friday, August 26, 2022, a new pedestrian route will be implemented on the north side of Eglinton Avenue between Gilgorm Road and Latimer Avenue to accommodate sidewalk construction. Pedestrians will be rerouted south around the work zone (refer to map). This configuration will remain in place for approximately two (2) weeks.

August 26 2022

Pedestrian Route Change at Chaplin Station - August 26, 2022

What Work is Taking Place?

As early as Friday, August 26, 2022, a new pedestrian route will be implemented on the north side of Eglinton Avenue between Gilgorm Road and Latimer Avenue to accommodate sidewalk construction. Pedestrians will be rerouted south around the work zone (refer to map). This configuration will remain in place for approximately two (2) weeks.

August 25 2022

Update: Notice of Water Shut-off NEW DATE: - Friday, August 26, 2022

What Work Is Taking Place?

On Friday, August 26, 2022, crews will perform watermain works at Chaplin Station.  A water shut-off is required to facilitate the work. The water shut-off will start as early as 8:00 a.m. for approximately eight (8) hours. Water service will be restored upon completion of the work. Please carefully read the water shut-off details below.

Water Shut-off Details: