In February 2016, crews began conducting preparatory activities in the Eglinton Avenue East vicinity to make way for the future Eglinton Crosstown LRT.
Upcoming works – geotechnical testing Read more »
The Crosstown team appreciates the patience of our neighbours and local businesses while we work to build new rapid transit. In 2015, the project made significant progress and hit a number of key milestones. We would like to take this opportunity to reflect on the past year and provide a look ahead to how we expect the project to progress in 2016. Read more »
As you know, tunnelling continues on the Eglinton Crosstown Light Rail Transit (LRT) project as we build the underground portion of the future transit line.
The tunnel boring machines (TBMs) operate around the clock - 24 hours a day, seven days week. On average, they each travel about 10 metres per day. Our TBMs are working about 20 metres below ground, but we do sometimes hear from nearby residents who may experience vibration from the TBMs as they pass through the area. Read more »
Metrolinx is making progress on the Crosstown project. Construction of a launch shaft east of Brentcliffe Road is complete and assembly of two tunnel boring machines (TBMs) is nearing completion. Utility relocation and headwall construction along Eglinton Avenue East between Brentcliffe and Bayview started in January 2014. Some works along the road have been completed and others are progressing well. The Crosstown Team appreciates the patience of our neighbours while we work to build transit. Read more »
The Eglinton Crosstown Project is building the Eglinton Line, a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with a 10-kilometre underground tunnel in its central section. When it’s complete, the line will connect Mount Dennis in the west to Kennedy Road in the east, and will be up to 60% faster than bus service today. Read more »
The Eglinton Crosstown LRT tunnel boring machines 'Don' and 'Humber' will begin their journey westward on September 29, 2015, marking another milestone toward the completion of the new LRT.
The westbound tunnelling will start from the launch shaft located east of Brentcliffe Rd. and will proceed towards Yonge St. Work on the western segment of the tunnel has been underway since June 2013 with four of the 6.5 kilometres already complete. All tunnelling work is expected to be finished by the end of 2016. Read more »
Pedestrian Information
Please cross the streets at corners with traffic lights or stop signs. Crossing in the middle of a block can be dangerous. Read more »
What/Where: Crews will be installing a hydro pole on City of Toronto property near 666 Eglinton Avenue east.
Why: The next stages of Emergency Exit Building construction near Leaside High School requires some hydro utility relocation. Specifically, a hydro pole needs to be installed and overhead hydro wires relocated.
When: Read more »
What work is starting?
What: Enbridge Gas Distribution will be relocating natural gas pipelines for the construction of the Eglinton Crosstown tunnel and future Don Mills Station. Read more »