Starting May 25, six (6) Light Rail Vehicles (LRVs) will be moved from the Eglinton Maintenance and Storage Facility (EMSF) to the LRT tracks (guideway) at Rosemount Dr. via truck transport. The LRVs will be delivered one at a time, on May 25, 26, 27, 31 and June 1 and 2.
Construction updates for stations and stops including: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O'Connor.
Original Post: April 23, 2021
Updated: April 28, 2021
Overnight OCS Cable Installations on Eglinton Avenue East between Don Mills Road and Sloane Avenue
WHAT WORK IS TAKING PLACE? Read more »
Original Post April 12 Read more »
UPDATED OCTOBER 23, 2020
What Work is Taking Place?
Shelter installation has been ongoing across the surface alignment for the Eglinton Crosstown LRT, beginning October 26, 2020, crews will perform glazing installation at the Wynford, O'Connor, Golden Mile and Birchmount stop shelters. Glazing consists of glass Installation works for the LRT shelters.
What to Expect Read more »
What Work is Taking Place?
Crews will begin installing duct banks under the West Don River Bridge as early as October 5, 2020. To perform this work safely, an alternating lane closure under the bridge will be in place for approximately six (6) weeks. Access to the E.T Seaton Park parking lot, south of Eglinton Avenue East will be maintained. There will be no impacts to traffic on Eglinton Avenue East.
Experience Eglinton by street: