What work is Taking Place?
What: With utility work and secant piling installations on the south side of Eglinton complete, work will return to the north side of Eglinton at Petman. During this stage, crews will continue to relocate utilities.
Why: Construction of emergency exit buildings requires utilities to be safely relocated. Depending on site conditions, this could include moving gas, hydro, water mains, sewers, and telephone lines, traffic lights and street lighting.
When: Starting as early as mid-June, 2016, crews will occupy the roadway on the north side of Eglinton Avenue East, for approximately three months. Some work may be rescheduled or adjusted due to weather conditions and unforeseen circumstances.
Where: The work zone will extend from approximately west of Cardiff Road to east of Falcon Street and will occupy the north lanes of Eglinton Avenue East.
Traffic Details
Pedestrian Information
For safety reasons, pedestrians will be separated from construction with concrete barriers and fencing. Please watch for additional signs directing pedestrians. Please take care when travelling near construction areas.
Transit Information
For the safety of transit riders, both eastbound and westbound TTC bus stops in the affected area will be relocated. Watch for posted signs and future information indicating the new locations.
Work Hours
Most of the work will be carried out between 7:00 a.m. and 11:00 p.m., 7 days a week. In certain situations, some late night and/or early morning works may be required to complete the work and keep construction moving. The contractor will not always work during the extended hours, but may do so at its discretion.
Noise and Vibration
Noise and vibration associated with construction can be expected with this work.
Thank you for your patience as we work to build this important project.
Please support your local businesses during construction.