Bell Utility Relocations at Leaside Station

August 29, 2016

What work is taking place? 

  • To prepare for future construction of Leaside Station, crews will complete substantial utility relocations around the intersection at Eglinton Avenue East and Bayview Avenue.
  • The first stage of utility relocations includes relocation of existing underground Bell utilities.

Timing

  • Work is expected to begin as early as early October 2016, and will continue until approximately late January 2017.
  • Work is permitted between the hours of 7:00 a.m. and 11:00 p.m., 7 days a week.
  • Occasional overnight work may be required – Metrolinx and CTS will notify the public in advance and monitor activities throughout.
  • Work may be rescheduled due to weather conditions or unforeseen circumstances.

What to Expect

  • Temporary work zone will be set up from 595 Eglinton Ave E to Bayview Avenue.
  • Work zone will be separated from traffic by jersey barriers and from pedestrian routes by temporary fencing.
  • During certain stages of the work, metal plates may be used to facilitate traffic and pedestrian movements.
  • Residents and businesses near the construction site should anticipate noise from excavators, bobcats, and other construction equipment caused by utilities relocation activity and removal of debris.

Map showing the work zone set-up in the curbside, eastbound lane on Eglinton Avenue East, from 595 Eglinton Avenue East to Bayview Avenue.

Traffic Details

  • This work will require the closure of the curbside, eastbound lane on Eglinton Avenue East, from 595 Eglinton Avenue East to Bayview Avenue.
  • Access to the parking lot entrance for 1750 Bayview Avenue will be maintained.

Pedestrian Details

  • Pedestrians will be rerouted around work zone and will be separated from traffic using jersey barriers.
  • A minimum of 1.5 m maintained for pedestrian movements.
  • Access to businesses will be maintained.

Transit Details

  • Relocation and re-routing of bus stops is done in consultation between TTC and Metrolinx to ensure construction can continue safely while minimizing impact on the community and customers.
  • The bus stop on the southwest corner of Eglinton Avenue East and Bayview Avenue will not be in service for the duration of this work.
  • All routes (#34, 51, 54, 56, 100, 334, 354) will stop on the southeast corner, on the far side of the intersection.
  • TTC signs will be posted for transit users.

 

For more information, please contact Nicole DiCarlo at the East Community Office. 

Thank you for your patience as we work to build this important project.