Allen Road South Closure for Utility Work at Cedarvale Station

March 17, 2018

What Work is Taking Place?

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating a sewer main across Allen Road South. The work will involve trenching for and installing a new sewer main, and removing the existing one. In order to safely carry out the work and mitigate impacts to traffic, Allen Road South will close south of Lawrence Avenue for the duration of the work.

Timing

  • The work is expected to take place on March 17th and 18th with rain dates of March 24th and 25th.
  • Work will occur during regular day-time hours from 7am – 11pm.


What to Expect

  • Allen Road South will close south of Lawrence Avenue for the duration of the work.
  • Construction zones will be instated on Allen Road South, north of Eglinton Avenue.
  • Nearby residents and businesses can expect noise in the area caused by an excavator, crane, loaders, trucks and other construction equipment, as well as dust from drilling activity and debris removal.
  • In addition to construction activity, residents can expect to see equipment and material storage within designated work zones.
  • The contractor may not always work during the permitted hours, but may do so at its discretion.

Transit Access

  • Access to the TTC Eglinton West Subway Station will be maintained at all times.

Travelling Smart During Construction

  • Travel delays are expected with construction. Please allow extra time for your journey.
  • Traffic will be extra heavy at peak periods during the Eglinton Crosstown LRT construction.
  • Download the free ‘aCrosstown’ traffic app to get real-time traffic and transit information for Eglinton Avenue.

Stay Informed

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.