TRAFFIC CHANGE FOR CHAPLIN STATION

May 23, 2018

What Work is Taking Place? 

In late February, crews began support of excavation activities on the north side of Eglinton Avenue.  As early as Saturday, May 26, 2018, crews will implement a new traffic stage at the intersection of Chaplin Crescent and Eglinton Avenue West.  Traffic will be shifted to the south side of Eglinton Avenue, while work is carried-out on the north side.

This traffic stage is expected to remain in place for the remainder of 2018.  Gilgorm Road and Latimer Avenue will remain closed for the duration of this stage.

Construction Staging

When?

  • As early as May 26, 2018 and for the remainder of 2018.
  • Permitted construction hours are 7:00 a.m. to 11:00 p.m.
  • Work may be delayed due to unforeseen circumstance

What to Expect

  • Gilgorm Road and Latimer Avenue will remain closed for the duration of 2018.
  • Pedestrians will be rerouted around the Main Entrance site.
  • Noise from construction activity can be expected.
  • Fencing, concrete barriers, scaffolding and signage will be erected around work zones.
  • Pedestrians and road users can expect delays when travelling through the intersection.

Traffic Changes

  • Gilgorm Road and Latimer Avenue will be closed at Eglinton Avenue West
  • Pedestrian rerouting will be in effect.
  • Turn restrictions will be in effect at the intersection of Chaplin Crescent and Eglinton Avenue.
  • The west and southeast driveway of Shoppers Drug Mart will remain open. 

 