NEW DATES: Road Resurfacing and Fresh Line Painting Work - Bessborough Drive to Hanna Road - (Overnight Lane Reductions)

October 10, 2018

PREVIOUSLY POSTED: SEPTEMBER 24, 2018

What Work is Taking Place?         

On October 12, 13 and 14, Eglinton Avenue East will be reduced to one lane, with two-way traffic facilitated by traffic control personnel between Hanna Road and Bessborough Drive.

Crews will re-surface the road decking and refresh lane markings in this area.  

Timing

  • Work will take place over three (3) nights - October 12, 13 and 14.
  • Work will occur between 9:00 p.m. and 7:00 a.m.  
  • Work may be rescheduled due to weather conditions or unforeseen circumstances.

What to Expect

Pedestrians, businesses and residents near the work site can expect to hear trucks, removal and replacement of existing line paint, movement of concrete barriers and fencing, and other construction equipment.