UPDATE: New Mining Activities at Laird Station
WHAT WORK IS TAKING PLACE?
As work progresses underground, final lining works will begin on sections of the caverns where mining excavation is complete.
- Waterproofing and final lining will occur inside of the complete caverns.
- Large concrete pours will be required periodically throughout final lining construction works.
- Concrete pours require continuous supply of concrete and at this time concrete will be delivery to tunnel level via the Main Entrance site.
TIMING
- Between late November and the end of 2018 there will be at least three (3) concrete pours.
- Continuous pours will last between 10 – 14 hours and will begin at 7:00 a.m.
- Mining works occur on a 24 hour schedule.
WHAT TO EXPECT & TRAFFIC AND PEDESTRIAN IMPACTS
- Approximately 54 concrete trucks will be required per pour, an average of 5 trucks per hour.
- Three trucks will be staged at a time inside of the Main Entrance site.
- Trucks will enter the north side of the construction site from Eglinton Avenue East and leave from the east side of the site on to Laird Drive.

Disponible en francais
For more information, please contact the East Community Office.
Thank you for your continued patience as we work to build this important project.