In late May 2020, crews began chipping a concrete wall located between the Chaplin Station Tertiary Entrance and the station box. This work will continue from June 9 through June 13, 2020 between the hours of 7:00 a.m. – 11:00 p.m. Chipping is the process of using an excavator and jackhammer to remove concrete and hardened material. Chipping occurs periodically as deep excavation progresses. Noise and vibration can be expected.
Hours of Work
Work Map Area
What to Expect
Travelling Smart during Construction
Travel delays are expected with the Crosstown construction. Please allow extra time for your journey. Traffic will be extra heavy at peak periods during the Crosstown construction. When possible, please travel during the off-peak period between 10 a.m. and 3 p.m.
Stay Informed
Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the Crosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.