What Work is Taking Place?
Crews at Fairbank continue to perform large concrete pours. On Friday December 11, work will begin as early as 7:00am and the pour will be ongoing for approximately five hours. Concrete pumps will be placed in the laneway parallel to Eglinton Ave W, south of the intersection. Concrete trucks will be staged on Dynevor Rd. The laneway parallel to Eglinton Ave W between Dynevor Rd and Dufferin St will be closed for the duration of the pour. Dufferin St and Eglinton Ave W will remain open while this work takes place.
What to Expect
Concrete trucks will be staged on Dynevor Rd. Access to properties along Eglinton Ave W, Dufferin St, and Dynevor Rd will be maintained. Noise from concrete trucks can be expected.
TRAFFIC IMPACTS
PEDESTRIAN IMPACTS
HOURS OF WORK
Disponible en français.
Experience Eglinton by street: