What Work is Taking Place?
As early as Wednesday March 10, 2021, crews will be installing underground conduits crossing Eglinton Ave W at Black Creek Dr for permanent street lighting and traffic signals. Work will take place in four phases, with three stages per phase. Each phase is expected to take approximately seven days to complete. Work will take place within regular working hours, from as early as 7:00am – 11:00pm. When crews are not working, they will install steel-plates over the area and all lanes will reopen.
What to Expect
Crews will be installing conduits crossing Eglinton Ave W at Black Creek Dr. There will be four phases to complete this work, one for each intersection crossing. One lane in each direction will always remain open. Lighting and noise from construction equipment can be expected.
HOURS OF WORK
TRAFFIC DETAILS
PEDESTRIAN DETAILS
Sign up for e-mail updates at www.thecrosstown.ca/sign-up