What Work is Taking Place?
As early as Monday, May 9 through to Friday, May 13, 2022, and on Monday, May 16 through to Friday, May 20, 2022, crews at Laird Station will be performing electrical works on Eglinton Avenue East by the Main and Secondary Entrance. To facilitate this work safely, lane reductions will be in place on Eglinton Avenue East by the Main and Secondary entrance. This work will take approximately three (8) days to complete and will be carried out in three phases (refer to maps). Please carefully read the details below.
Expect delayed while travelling through the area. Noise from construction activities can be expected. Traffic control personnel and/or a Paid Duty Officer will be present, for the duration of this work.
HOURS OF WORK
o Phase One: One (1) day
o Phase Two: One (1) day
o Phase Three: One (2) days
TRAFFIC DETAILS
Phase One: Westbound traffic on Eglinton Avenue East will be reduced to one lane west of Laird Drive.
PEDESTRIAN DETAILS
TRANSIT INFORMATION
Experience Eglinton by street: