What Work is Taking Place?
As early as Sunday May 26 for approximately 5 days, crews will work overnight install a hydro utility duct bank structure on Eglinton Avenue between Mt Pleasant Road and Brownlow Avenue. This work requires rolling lane closures. Eglinton Avenue will be reduced to one lane only, alternating traffic in each direction, while this work takes place. To minimize the impact to the travelling public, this work will be performed overnight, when traffic is lighter. Crews will endeavour to minimize disruption as much as possible.
Hours of Work
- Sunday May 26 – Friday May 31, 2019
- 10:00 p.m. – 5:00 a.m.
- This work may be delayed or rescheduled due to inclement weather or unforeseen circumstances
Construction Configuration
Work will take place in the area shown in red:
What to Expect
- Overnight noise from construction equipment, such as and excavator, hydro-vacuum, trucks and generator, as well as site lighting can be expected
- Eglinton Ave will be reduced to one lane only between Brownlow Ave and Mt Pleasant, alternating traffic in each direction using traffic control personnel
- Expect delays when travelling through the intersection
Disponible en francais