Crosstown

Allen Road

October 112018

Eglinton Avenue West Lane Restriction For Signal Installations At Cedarvale Station

What Work Is Taking Place?

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating and installing new traffic poles and signal equipment along Eglinton Avenue West from Park Hill Road to Allen Road North.

Hours of Work Read more »

October 112018

Overnight Work For Curb Realignment At Cedarvale Station

What Work Is Taking Place?

 To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be realigning a curb along Eglinton Avenue West from Everden Road to Strathearn Road.

Hours of Work Read more »

October 092018

UPDATE: Allen Road South Closure October 19th-22nd Due To Exit Ramp Reinstatement

Originally Published: October 4, 2018

Updated: October 9, 2018  

What Work is Taking Place

  • Continued supporting of excavation for the new Eglinton LRT Cedarvale Station requires the Allen Road South exit ramp be reinstated to its original position.
  • The ramp will be closed and reinstated over a weekend.

 Hours of Work Read more »

October 052018

UPDATE: Upcoming Traffic And Pedestrian Changes At Eglinton West Subway Station (Cedarvale)

Originally Published: September 21, 2018

Updated: October 5, 2018

What Work Is Taking Place?

In Fall 2018, the area around Eglinton West Subway Station (Cedarvale) will see another round of changes.  Pedestrian routes to the station will be rerouted and traffic lanes will shift.

Hours of Work Read more »

September 192018

Upcoming Toronto Hydro Relocation Work At Cedarvale Station

What Work is Taking Place? 

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating Toronto hydro infrastructure in the area of Everden Road and Eglinton Avenue West. For pedestrians travelling north on Everden Rd the ONLY access to Eglinton Avenue West will be through Ben Nobleman Park. Pedestrians will be routed through the pre-existing paved pathway through Ben Noblemen Park to the sidewalk on Eglinton Avenue West. Read more »

August 142018

Overnight Work Eastbound Eglinton Lane Closures

Cedarvale Station: Overnight Work  - Eastbound Eglinton Lane Closures Read more »

July 262018

Cedarvale & Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill Stations was held on July 25, 2018. You can view the presentation here:

Download the presentation

June 282018

Upcoming Traffic and Pedestrian Changes at Eglinton West Subway Station (Cedarvale)

Original Posting Date: June 18, 2018

In mid-July 2018, the area around Eglinton West Subway Station (Cedarvale) will see another round of traffic changes.  Work zones will move to the north side of Eglinton Avenue. The Allen Road exit ramp will be realigned, pedestrians will no longer be able to access the subway from the north side of Eglinton Avenue and active traffic lanes will shift south.  Read more »

June 282018

Cedarvale & Forest Hill Construction Liaison Committee Meeting

The presentation for the construciton liaison committee meeting of Cedarvale and Forest Hill Stations for the month of June 2018 can be viewed here:

Download the presentation

June 282018

Allen Road South Closure - July 13-16 - Exit Ramp Re-Alignment

Original Posting Date: June 18, 2018

What Work is Taking Place

Supporting the excavation of the new Eglinton LRT Main Entrance requires the Allen Road South exit ramp to be realigned 20 meters to the west of its current position. Read more »