What Work is Taking Place?
Crews will be constructing final sidewalks at the north-east and south-east corners of the Eglinton Ave E and Pharmacy Ave intersection. Work is expected to begin November 6, 2020 for a period of approximately one week.
What to Expect
What Work is Taking Place?
Crews will be installing Overhead Catenary System (OCS) cables along Eglinton Avenue East, between Victoria Park Avenue and Pharmacy Avenue. OCS is the system installed overtop of the rails of a light rail system, to provide operational power to the Light Rail Vehicles (LRV’s). Installation will take place October 19-23 and 26-30, 2020 between the hours of 9:00 p.m. and 6:00 a.m.
Construction Liaison Committee of Pharmacy to Kennedy was held on September 29, 2020. You can see the presentation here:
Construction Liaison Committee of Pharmacy to Kennedy was held on July 28, 2020. You can see the presentation here:
Construction Liaison Committee of Pharmacy to Kennedy was held on May 26, 2020. You can see the presentation here: