Crosstown

Construction Updates

September 212018

Upcoming Traffic and Pedestrian Changes At Eglinton West Subway Station (Cedarvale)


In Fall 2018, the area around Eglinton West Subway Station (Cedarvale) will see another round of changes.  Pedestrian routes to the station will be rerouted and traffic lanes will shift.

Hours of Work Read more »

September 212018

Driveway Closure on Eglinton Ave West and Alternative Parking

564 EGLINTON AVE W DRIVEWAY CLOSURE AND ALTERNATIVE PARKING

 

What work is taking place? Read more »

September 192018

Pedestrian Changes at Forest Hill Station

What Work Is Taking Place

A pedestrian change has been implemented at Forest Hill Station. Pedestrians will be rerouted around the Station’s Secondary Entrance site on north side of Eglinton Avenue West, just west of Bathurst Street. This change is required in order to make way for shoring and utilities work in the northwest station box area.

Pedestrian Impacts Read more »

September 192018

Upcoming Toronto Hydro Relocation Work At Cedarvale Station

What Work is Taking Place? 

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating Toronto hydro infrastructure in the area of Everden Road and Eglinton Avenue West. For pedestrians travelling north on Everden Rd the ONLY access to Eglinton Avenue West will be through Ben Nobleman Park. Pedestrians will be routed through the pre-existing paved pathway through Ben Noblemen Park to the sidewalk on Eglinton Avenue West. Read more »

September 192018

Curb Installation on Eglinton Avenue at West Portal

 

 

What Work is Taking Place?

As part of continued construction of the West LRT Portal and Elevated Guideway, crews will be installing a new curb along the south side of Eglinton Avenue West from Black Creek Drive to Keelsdale Park Road. Read more »

September 192018

Temporary Traffic Changes at East Don River Bridge to Facilitate Early Morning Deck Pour

What Work is Taking Place?

The East Don River and Wynford Drive Bridges are being rehabilitated as part of the construction of the Eglinton Crosstown LRT. Works include deck replacement, reinforcement, and repairs to the supports and beams to both bridges.

As part of the ongoing works crews will be conducting deck pouring at the East Don River Bridge. This work is scheduled to start as early as Saturday, September 22nd  — to facilitate this work there will be a temporary traffic staging. Read more »

September 182018

UPDATE: Traffic and Pedestrian Changes - Leaside Station

Over September 24 and 25, the traffic conditions at Bayview Avenue and Eglinton Avenue East will change. Please review the changes to lane configurations and turn restrictions on the map below.

The new temporary traffic signals are now operating at Bayview Avenue and Roehampton Avenue. Read more »

September 182018

Construction Notice - Mount Pleasant Station - Watermain Repair Update

UPDATE ON WATERMAIN REPAIRS AT MOUNT PLEASANT STATION

Information as of 5:00 p.m. on September 18, 2018 

 

What Work is Taking Place?

On Monday September 17, 2018, a watermain ruptured during support of excavation activities on the southwest corner of Mt. Pleasant Road and Eglinton Avenue East. Read more »